CHS Softball Field

Design Approval Process

December 2021

Initial meeting between architectural firm and CHS and District Staff

March 2022

Design development completed

July 2022

Plan submitted to Division of State Architect for approval

December 2022

Division of State Architect approval of plan

Construction Timeline

April 7 & 14, 2023

First and Second Notice Inviting Formal Bids 

April 20, 2023

Job Walk

May 4, 2023

Bid Opening

June 1, 2023

Recommendation to Board of Education to Award Bid

June 19, 2023

Begin Work - Pending Board Approval of Bid Award

February  2024

Estimated Completion Date